Consort Healthcare were commissioned to provide a £170m extension to the Victoria Hospital in Kirkcaldy under a PPP contract, on behalf of NHS Fife.  In conjunction with this project, a substantial amount of additional work was required on the existing estate to facilitate the operation of the new hospital.

CPC provided project management services for these additional works under the NEC3 contract (Option C) over a six-year period, with fixed milestones at various stages of the programme.

The work was separated into three categories –

  • Pre-PPP – works which had to be completed in advance of the start of construction works on the PPP scheme, including ground clearance, decontamination and service re-diversion works
  • Para-PPP – works to be carried out in conjunction with the PPP, providing essential services which had to be available for the opening of the extension, such as the new service yard, laboratories and data centre
  • Post-PPP – works which could not be carried out until the PPP extension was occupied, such as conversion of disused wards into offices, and creation of a new mortuary in the old endoscopy area


featured image

Our services

  • Programme management
  • Project management
  • Stakeholder management
  • Cost management
  • Quantity surveying
  • CDM co-ordination
  • Site supervision
  • Migration management


This project was the pilot scheme for the use of the NEC3 contract on healthcare projects in Scotland.

Download brochure

  • I'd like to receive updates from CPC Project Services
  • I agree to CPC's Terms of Use

Featured projects.

Cancer Treatment Centre, Manchester

Read More

The Christie NHS - Capital PMO

Read More

Mental Health Estates, SLaM NHS

Read More

Get in touch

If you would like to speak to us, then we would be delighted to hear from you.

Contact us!

Simply fill in the form below and submit your enquiry